Give Push to your Success with SAP Certified Application Associate C_S4PPM_2021 Exam Questions
C_S4PPM_2021 100% Guarantee Download C_S4PPM_2021 Exam PDF Q&A
SAP C_S4PPM_2021 certification exam consists of 80 multiple-choice questions, and the candidate has 180 minutes to complete the exam. C_S4PPM_2021 exam covers various topics related to SAP S/4HANA Portfolio and Project Management, including project management fundamentals, project planning, project execution, project monitoring and controlling, and project reporting. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification exam also assesses the candidate's ability to configure and implement SAP S/4HANA Portfolio and Project Management solutions. Upon successful completion of the SAP C_S4PPM_2021 certification exam, candidates will be recognized as certified SAP professionals in the field of Portfolio and Project Management.
SAP C-S4PPM-2021 exam is an industry-recognized certification that validates the skills and knowledge required for Portfolio and Project Management professionals using the SAP S/4HANA system. Certified Application Associate - SAP S/4HANA Portfolio and Project Management certification exam is designed to test the candidate's knowledge of the application of SAP Portfolio and Project Management in a business environment. C_S4PPM_2021 exam is intended for individuals with a good understanding of the features and functionalities of the SAP S/4HANA system, as well as those who are experienced in project management.
SAP C-S4PPM-2021 certification exam consists of 80 questions and has a time limit of 180 minutes. C_S4PPM_2021 exam is available in English and is conducted online. The passing score for C_S4PPM_2021 exam is 65%. C_S4PPM_2021 exam fee for this certification is $550.
NEW QUESTION # 42
No upcoming milestone are shown in the my projects SAP Fiori app.
What are the reasons for this?
NOTE: There are 2 correct answers to this question
- A. Milestone is not identified as critical
- B. You are not defined as the project Responsible
- C. Milestone is not identified as mandatory
- D. Project is not released
Answer: B,D
NEW QUESTION # 43
You staff a resource to a project.
Where is the default authorization for the resource defined?
- A. In the project
- B. In the project template
- C. In customizing for role functions
- D. In customizing for role types
Answer: D
NEW QUESTION # 44
How do you make a decision point field a required field for a specific portfolio item?
- A. Make the filed a required field for the decision point and assign the item type to the portfolio In customizing
- B. Make the filed a required field for the combination of the item and decision point in customizing for the portfolio type
- C. Make the field a require field for the combination of decision point and portfolio type in customizing for the item type
- D. Make the filed a required field for the combination point and assign the item and decision point in customizing for the portfolio type
Answer: B
NEW QUESTION # 45
You have defined a financial view for portfolio bucket so that financial values are rolled up.
Which of the following are possible sources for the rollup?
NOTE: There are 3 correct answers to this question
- A. Project management projects
- B. Initiatives
- C. Project system project
- D. Standalone items
Answer: B,D
NEW QUESTION # 46
Bucket A contains items and current located in bucket P1.
How do you move bucket A including the items to bucket p2.
- A. Move all items from bucket A to bucket p2.
Move the empty bucket A to p2
Copy all bucket A items from bucket p2 to bucket A - B. Create a new bucket in bucket P2
Move all items from bucket A to the new bucket
Delete bucket A and rename the new bucket - C. Select bucket p2 in the move function as a target for bucket A
Execute the move function - D. Select bucket A from the bucket dashboard
Change the parent bucket field from P1 to P2
Answer: B
NEW QUESTION # 47
You want to use a customer-specific status for items.
How do you configure the status in customizing?
- A. Create the status and status transition within the portfolio type
Assign the portfolio item type to the portfolio type - B. Create a business add-in (BAdi) for customer-specific status management Activate the BAdi for the portfolio item type
- C. Create the status
Assign the status to a portfolio item type
Specify the status transitions with respect the portfolio item type - D. Create a status profile for the portfolio item objet type
Create the status within the status profile
Assign the status profile to a portfolio item type
Answer: C
NEW QUESTION # 48
How can you trigger a workflow for a portfolio item?
NOTE: There are 2 correct answers to this question.
- A. Change the item status
- B. Exceed the budget of the item
- C. Change the master data of the item
- D. Choose the start workflow button
Answer: A,C
NEW QUESTION # 49
Which objects can used to record times in Cross-Application Time Sheels (SAP Cats)?
NOTE: There are 3 correct answers to this question
- A. Task
- B. Role
- C. Phase
- D. Checklist item
Answer: A,B
NEW QUESTION # 50
You have created a portfolio with the bucket levels and wants to create a portfolio item.
When can you create the portfolio item?
- A. At the lowest bucket level
- B. At multiple bucket levels
- C. At the highest bucket level
- D. At any bucket level
Answer: A
NEW QUESTION # 51
You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.
How do you make this selection available?
- A. Run a report to enable the consultant role type
- B. Assign the consultant role type to the appropriate item type
- C. Activate the consultant role type
- D. Assign the consultant role type to the appropriate project type
Answer: D
NEW QUESTION # 52
When is Bottom-up scheduling mandatory?
- A. When constraints are used
- B. When actual time are recorded
- C. When parallel phasing is used
- D. When summary tasks are used
Answer: D
NEW QUESTION # 53
You want to control the execution of subsequence phases in project management.
Which indicators must you activate in the phase type in customizing?
NOTE: There are 2 correct answers to this question
- A. The completion required indicator
- B. The approval phase indicator
- C. The complete phase when Granting Approval indicator
- D. The Release Success phase only after Approval indicator
Answer: B,D
NEW QUESTION # 54
What are prerequisites for using cross-Application time sheet (SAP CATS) to confirm In a project management project?
NOTE: There are 3 correct answers to this question.
- A. Accounting integration for this project is active
- B. The role type must allow time recording with CATS
- C. The planned efforts is on the task
- D. The project type must allow time recording with the CATS
Answer: A,D
NEW QUESTION # 55
When you confirm a task, you wants the system to calculate the difference between planned work and actual work.
What must you do?
- A. Ensure that the Rem. Work manually indicator is inactive
- B. Confirm the task using a completion percentage of less than 100
- C. Enter an actual finish date of the task in the future
- D. Set the task status to in process
Answer: A
NEW QUESTION # 56
Resources are not shown in the Resource Overview
What is the reason for this?
NOTE: There are 2 correct answers to this question
- A. Assignment of resource management authorization object is missing
- B. Resource pool assignment is missing
- C. Project response assignment
- D. Staffing manager assignment is missing
Answer: B,D
NEW QUESTION # 57
You have defined an item template. When you create a new item, you notice that you cannot select the template.
What could be the reason for this?
NOTE: There are 2 correct answers to this question
- A. The item template is not available in the selected bucket
- B. The item template start date is in the future
- C. The item template has a different item type
- D. The item template has the Activate status
Answer: A,C
NEW QUESTION # 58
In portfolio management to which of the following does the logical system refer In the definition of the PS project definition object link?
- A. Business intelligence (BI) system for reporting
- B. Target system for integration
- C. BCV system for reporting
- D. Web server for integration
Answer: B
NEW QUESTION # 59
What data can you synchronize between a portfolio item and an initiative using Decision Flow management?
- A. Notes
- B. Documents
- C. Metrics
- D. Development Cost
Answer: D
NEW QUESTION # 60
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?
- A. Mass update
- B. XML upload
- C. Distribution function
- D. Drag and drop
Answer: C
NEW QUESTION # 61
Which of the following are consequence of releasing a phase?
NOTE: There are 2 correct answers to this question
- A. Predecessor phases are assigned the status locked
- B. Lower-level tasks and checklist are release
- C. The phase type is set to read-only
- D. Additional tasks cannot be added to the phase
Answer: B,C
NEW QUESTION # 62
Which of the following can you use to create multiple portfolio items simultaneously?
- A. Primavera import
- B. Microsoft project import
- C. Microsoft Excel import
- D. Item template
Answer: D
NEW QUESTION # 63
......
Get C_S4PPM_2021 Actual Free Exam Q&As to Prepare Certification: https://freetorrent.braindumpsvce.com/C_S4PPM_2021_exam-dumps-torrent.html